Chapter 15.66 ARCHITECTURAL REVIEW BOARD
Section 15.66.090 Review Procedure.
The Architectural Review Board shall be required to review and make its recommendation
to
the City Council upon building permit applications referred to the board within thirty (30) days
of the date such application and all required supporting documents (including construction plans,
elevation studies, site plans, drawings and specifications, etc.) is filed with the board by the
Building Commissioner, unless the applicant and the board jointly agree to extend the time for
board review. For board reviews involving a certificate of appropriateness issued by the
Columbia Heritage and Preservation Commission, the time for completion of the Architectural
Review Boards review will not commence to run until the board has received the certificate of
appropriateness and the recommendation of the Columbia Heritage and Preservation Commission
regarding the issuance of the building permit. Board recommendations shall be forwarded to the
City Council for action at the next successive regular meeting of the City Council to be held not
less than five (5) days after the decision of the board. The City Council shall be required to
make its decision regarding the building permit application within thirty (30) days after the
Architectural Review Board has made its recommendation regarding the issuance of the building
permit. Failure of the City Council to act within the time aforesaid shall be deemed approval
of
the application and shall authorize the Building Commissioner to issue the building permit,
provided the applicant has otherwise complied with City Ordinance requirements for building
permit issuance.
(15.66.090, Added, 03/07/2005, Review Procedure.)