Section 15.52.080 Construction of facilities.
The stormwater detention facilities shall be built in conjunction
with the storm sewer
installation and be fully operational after the clearing of vegetation.
A. Silt and debris connected with
early construction shall be removed periodically from the
detention area to maintain full storage capacity.
B. The maintenance responsibility
of the detention area shall remain with the developer
and/or contractor until final inspection and applicable construction performance guarantees are
released.
C. Before final plat approval and
before approval of subdivision improvement plans by the
city, the developer shall submit his commitment for future maintenance responsibility of the
detention area. The city may withhold final plat approval and approval of improvement plans
unless adequate arrangements are made to provide for the future maintenance of the detention
area by the developer or the property owners in the subdivision benefitted thereby. (Ord. 1320 §
1 (part), 1995: prior code § 5-7-1(H))